
Lund worked with the Owners, Jim and Rae Hunter of Matagouri
Trackers Ltd from the beginning of the design phase right through
to completion to bring this very high quality building of 2500m2,
on 4 levels, to fruition, on a strictly controlled budget. The
building was speculative, in that there were no confi rmed tenants
when construction commenced. The Owner acted as the project manager
in concert with our Site Engineer. The main contract work and some
subtrades were completed on a time and materials Maximum Price
basis, which was the appropriate method to accommodate the many
changes required by tenants. Other trades were tendered as the
documentation became available, and design decisions made. There
were over 40 subtrades in this project. Lund's provided a
comprehensive administration and financial monitoring service to
the Owner. To effect this work, Lund's placed a quantity surveyor
onsite full time and provided a site engineer 16-32 hours a week in
addition to a senior foreman onsite.
The building occupied 98% of a CBD site in Queenstown, thus
staging, storage and craneage were problematic. Lund's solved these
problems by constructing a steel framed perimeter gantry corridor
around the 3 street frontages and purchasing a new state of the art
Liebherr self erecting tower crane for the project which occupied
an area of 4m x 4m-the only piece of land not built on! During
construction, a lack of subcontract resources created obstacles to
the programme. Lund's had to find inventive ways to keep the
project on track. There was a significant amount of architectural
precast work in the building.
(Plinths, sills, columns, lintels, balconies). Due to lack of
capacity for precast manufacture at the time, to keep the building
to programme, Lund's manufactured the basement panels and the
architectural lintels themselves in Dunedin.