Lund South completed the concrete structure contract in a 50/50
arrangement with Amalgamated Builders Ltd.
The South Stand, comprising a 10,856 seat stadium to the front,
and a 5 level 22m high, 130m long, 18,000 m2 building behind was
started on August 15 2009.
The main structure, to full height was completed by March 5 to
allow the stadium steel roof structure to proceed. It will be 100 %
complete by May 2010.
The South Stand structure was completed by both ABL and Lund
staff. ABL crews generally completed ground floor work, and precast
installation. Lund staff were generally responsible for all work
above the first level. Both ABL and Lund staff for all above ground
work were under the direction of a Lund senior foreman.
The North stand, an open 20m high structure seating 10,856, was
started on November 9 2009 and will be complete by April 30. It
would have been completed even earlier, by mid March 2010 if
precast supply was able to keep pace with construction onsite.
The North Stand structure, 130m long, involved structural
challenges not experienced before in the South Island - 15 degree
inclined precast columns, 16m high, weighing 40T. 28T L shaped
combination bleacher beam and upper columns, erected 16m in the
air.
The North Stand was constructed exclusively by Lund.
These feats of construction, on this scale, have not been
achieved before in Dunedin.